Bitcoin Mining Gets Three Month Reprieve From Hochul’s Regulators

Green groups charged that Kathy Hochul is punting the issue until after the primary.

Peter Mantius   ·   April 1, 2022
Greenidge power plant in Dresden, New York | Greenidge

Facing a major test on how the state plans to enforce its ambitious 2019 climate change law, state regulators on Thursday delayed for the second time a ruling on an air permit for a Bitcoin mining operation in the Finger Lakes.


Nearly a year ago, New York Focus reported that the once-shuttered power plant in Dresden, owned by Greenidge Generation, had fired back up again and now mines Bitcoin—and that dozens of other plants could follow, posing a threat to the state’s greenhouse gas reduction goals. 


Just six days ago, Greenidge proposed “mitigation measures” to reduce the plant’s emissions. And yesterday, the Department of Environmental Conservation said it needed three more months to consider those proposals.  In the meantime, the agency will allow Greenidge to continue operating its power plant in Dresden under its existing air permit.


In a statement released yesterday, the DEC said it had not yet determined the sufficiency of the company’s new proposals to reduce the power plant’s emissions by 40 percent below current permitted levels by 2025, and to turn the plant into a “zero-carbon emitting generation facility” by 2035.


This is the second time that DEC has delayed a decision on the company’s bid to renew the permit, which expired in September 2021 but has been administratively extended. Under the state’s Uniform Procedure Act, the DEC had faced a January 31 deadline to renew the permit, but said it needed two more months to review public comments.


Environmental advocates said the timing of the new deadline — eight days after Gov. Kathy Hochul’s primary election — suggests a political motivation on the governor’s part for postponing the ruling: to avoid alienating voters or contributors on either side of the issue until after the election.


“They Don’t Want To Make A Hard Decision”


Advocates had expected the DEC to announce on Thursday that it had denied the new permit, based on agency statements about the plant’s non-compliance with the state climate law. Some blame Gov. Kathy Hochul for the agency’s repeated delays.


“There’s more than enough information for the Hochul Administration to reject the permit if they were serious about the climate,” said Judith Enck, a former regional supervisor for the U.S. Environmental Protection Agency. “Seems like they just don’t want to make a hard decision.”


Liz Moran, a state policy advocate for Earthjustice, said Thursday’s DEC decision to delay ruling on the permit renewal “is a failure to the residents and businesses of the Finger Lakes” that will allow more greenhouse gas pollution.


Yvonne Taylor, vice president of environmental group Seneca Lake Guardian, said it was “outrageous that Gov. Hochul not only failed to act but punted a decision to after the primaries in an apparent attempt to cover her political interests.”


Hochul faces a Democratic primary for governor on June 22, just over a week before the DEC’s new deadline to act on Greenidge’s air permit. Current polls show her well ahead of challengers Jumaane Williams and Tom Suozzi, but others, including former Gov. Andrew Cuomo, could still join the race.


Assemblymember Anna Kelles (D-Ithaca) said the act of postponing a second time “is incredibly disappointing, and appears to be politically motivated.”


Kelles noted that DEC explicitly asked Greenidge last summer to explain how it intended to comply with the 2019 Climate Leadership and Community Protection Act, or CLCPA. 


After reviewing the company’s proposed explanation, DEC Commissioner Basil Seggos tweeted last September that “Greenidge has not shown compliance with NY’s climate law.”


The DEC went even further in a March 21 statement to the WaterFront blog: “Greenidge has ‘not shown compliance’ because the air application does not currently meet the requirements of the CLCPA, notably it has not to date shown that it is consistent or would not interfere with the attainment of statewide greenhouse gas emission limits; nor has it provided sufficient justification or identified alternatives or sufficient mitigation.”


Dale Irwin, manager of Greenidge’s Dresden plant, did not respond to a request for comment. Shares of Greenidge, which have slumped recently on the NASDAQ market, responded positively Thursday afternoon, as news of the DEC’s action began to leak. Shares rose from $8.18 at 1:20 p.m. to close at $8.56, a 4.5 percent jump. Year-to-date Greenidge shares have slipped about 50 percent.


Increased Capacity


Last week, Greenidge announced that it had arranged $108 million in new borrowing to help fund the purchase of more Bitcoin mining “rigs,” computing devices used to verify Bitcoin transactions and earn Bitcoin tokens.


“This is a transformative year for Greenidge as we expect to more than triple our datacenter capacity…with the vast majority of the capacity expansion focused outside of the company’s original site [Dresden] in New York,” Greenidge CEO Jeff Kirt said in a press release. The company opened a new facility in South Carolina three months ago. 


But even as it focuses on the new South Carolina plant, Greenidge has told investors that it plans to install thousands of new mining rigs in Dresden this year as it boosts the power needed to run them from 45 megawatts to 85 megawatts. Construction work on the expansion is currently underway.


That boost in energy generation guarantees corresponding increases in greenhouse gas emissions. 


Meager Mitigation


Greenidge’s widely-promoted plans for a rapid Bitcoin buildout last year sparked concerns that other older fossil fuel plants could adopt its business plan, threatening the state’s ability to comply with CLCPA emissions targets.


The environmental law group Earthjustice spelled out that prospect in a letter to the DEC last April, which warned that nearly 30 old power plants could follow Greenidge’s example if the agency allowed them to.


About that time, Greenidge applied to the DEC to renew its Title V air permit, which was due to expire in September 2021.


During its initial review of the renewal application last summer, the DEC required company officials to explain how they intended to comply with the CLCPA, which requires a statewide reduction in CO2-equivalent greenhouse gas emissions by 40 percent from 1990 levels by 2030.


In August, the company responded in a letter signed by David T. Murtha of the consulting firm Environmental Resources Management. Murtha detailed the potential emissions onsite from the plant itself and upstream from its source of power — natural gas wells and gas pipelines. 


“Comparing the combined upstream and onsite potential emissions to the 1990 baseline demonstrates a 70.3 percent reduction in GHG and CO2e emissions for the Greenidge facility,” Murtha wrote, referring to the plant’s performance three decades ago as an inefficient coal-burner. It converted to burning natural gas in 2017.


However, the letter also acknowledged that the combination of Greenidge’s potential onsite and upstream CO2e emissions totaled 1.05 million tons — 64 percent above the limit it now seeks in its renewal application. 


A chart included in Murtha’s letter showed Greenidge’s annual potential onsite and upstream emissions totaling 952,968 metric tons. That’s the same as 1.05 million regular, or “short,” tons (the measurement standard used by the DEC), including 573,626 tons onsite and 466,919 tons upstream.


Murtha projected that those total emissions of 1.05 million tons would remain at exactly those levels through 2026, despite Greenidge’s widely publicized plans to add thousands of new bitcoin mining machines and roughly double the energy needed to power them.


The August 2021 letter suggested several potential steps to be taken to mitigate the plant’s greenhouse gas emissions. But they were not enough to prevent Seggos from tweeting a month later that the company had not shown compliance with CLCPA.


https://twitter.com/basilseggos/status/1435724739352449025?lang=en


Robert Howarth, a Cornell University biochemist, said the climate law’s new requirement to count power plants’ upstream emissions was critically important. He sits on the state’s Climate Action Council, which is charged with implementing the CLCPA.


“I haven’t seen [Greenidge’s] proposal to mitigate emissions,” he said Thursday. “But I don’t see how it’s possible to operate the plant on fracked gas and significantly enough mitigate the emissions, a lot of which are methane from out of state.”


Banning Bitcoin


As the DEC has repeatedly delayed its decision on Greenidge’s air permit renewal, Assemblymember Kelles has been promoting a bill in the Assembly that calls for a statewide moratorium on the energy-intensive “proof-of-work” process that Bitcoin relies on. Her measure recently passed out of the Assembly Environmental Conservation committee and now awaits an Assembly floor vote. A similar bill awaits committee consideration in the state Senate.


Enck said Thursday’s DEC decision to postpone once again “should spur the Legislature to act to enact the [proposed Kelles] moratorium.”


Moran, of Earthjustice, said that even before the legislature passes Kelles’ bill, Hochul could use her executive branch authority to impose a temporary statewide moratorium on proof-of-work crypto mining, pending a full environmental review.


Earlier this month, a white paper produced by Columbia University’s Sabin Center for Climate Change Law argued that Hochul had ample legal authority to do so, relying on the precedent of New York’s 2010 executive branch moratorium on hydraulic fracturing of natural gas wells.


“We simply cannot let proof-of-work mining lead to this enormous energy consumption spike at a moment when climate scientists are collectively saying we must reduce our total greenhouse gas emissions,” Kelles said.

I hope this article helped you better answer the question that guides all of our journalism: Who runs New York? Before you click away, please consider supporting our work and making more stories like this one possible.

New York state is standing at a crossroads for climate action. After passing one of the nation’s most ambitious climate laws in 2019, the state is lagging far behind on its targets, struggling to meet deadlines to build renewable energy and clean up its buildings and roads. Other states are closely watching our progress, making decisions about their own climate plans based on New York’s ability to implement this legislation.

As New York’s only statewide nonprofit news publication, we’ve been scrutinizing the state’s climate progress. Our journalism exists to unpack how power works in New York, analyze who’s really calling the shots, and reveal how obscure decisions shape ordinary New Yorkers’ lives.

But we can't do this work without your help. We rely on reader donations to help sustain our outlet, and every gift directly allows us to publish more pieces like this.

Our work has already shown what can happen when those with power know that someone is watching, with my reporting prompting a state investigation and fine for a major corporation. I have more story ideas than I can count, but only limited resources to pursue all the leads that come across my desk.

If you’re able, please consider supporting our journalism with a one-time or monthly gift. Even small donations make a big difference.

Thank you for reading.

Colin Kinniburgh
Climate and Environmental Politics Reporter
Also filed in New York State

In a state known for scandals, Albany’s ethics enforcement has long been criticized.

A review of Trump’s first term, along with his campaign promises and details found within Project 2025, indicate what’s to come in New York.

Offshore wind is crucial to the state’s plans for cleaning up its electric grid, and construction is already behind schedule. The incoming president could slow it down a whole lot more.

Also filed in Climate and Environment

Some want New York to rethink its climate mandates. Could new gas plants be on the table?

Major new tech facilities are not expected to overload the state’s grid — but New York City could fall short of power in the early 2030s without creative solutions, according to a key study.

New rules from the Biden administration require water utilities to replace all lead pipes. That could cost New York $2.5 billion or more, kicking off a fight over who pays.